Your project has a Budget at Completion (BAC) of $200,000. If your project is planned to be 40% complete at this stage, what is the Planned Value (PV)?
$80,000
$120,000
$60,000
$100,000
Your project has a Budget at Completion (BAC) of $200,000. If your project is planned to be 40% complete at this stage, what is the Planned Value (PV)?
$80,000
$120,000
$60,000
$100,000
Planned Value (PV) represents the amount of work that should have been completed, based on the project plan. It is calculated using the formula PV = Planned % Complete x Budget at Completion (BAC). Here, PV = 40% x $200,000, which equals $80,000.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.