PMI Project Management Professional Practice Question

Your organization has adopted an agile approach to project management. As the project manager, you are tasked with preparing the schedule for a new software development project. Your team will work in iterations to deliver incremental value to the client. Which of the following is the most appropriate approach for preparing your project schedule?

  • Utilize a Scrum Board to visualize the backlog and allow the team to pull tasks for each iteration.

  • Set up a Kanban Board to manage and limit work in progress, ensuring continuous delivery of components.

  • Create detailed Gantt Charts outlining all the tasks and their dependencies for the complete project duration.

  • Prepare Release and Iteration Plans to schedule feature delivery across different iterations, aligning with the agile approach.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot