Project Management Professional Practice Question

Your ongoing project developing software for online banking is impacted by newly implemented financial regulatory requirements. As a project manager, how should you initially evaluate the necessary actions for scope adjustment?

  • You selected this option

    Inform all stakeholders about the regulatory changes

  • You selected this option

    Increase the project budget to accommodate any potential change

  • You selected this option

    Conduct an audit on the project’s technological capabilities

  • You selected this option

    Assess and prioritize the impact on project scope to determine necessary adjustments

Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot