Project Management Professional Practice Question

Your experienced UI designer estimated the "Design User Interface" activity at 80 work-hours based on her normal productivity of 8 productive hours per day. She will be unavailable for the first 5 working days, when a less-experienced designer, whose productivity you estimate at 6 productive hours per day, will cover the work. Afterward the senior designer returns. Assuming no other resources are assigned, what is the revised duration estimate in working days (round to the nearest whole day)?

  • 13 working days

  • 10 working days

  • 12 working days

  • 15 working days

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot