PMI Project Management Professional Practice Question

Your company is undergoing a major organizational change by implementing a new operational structure that influences the scope and resources of your ongoing project. What is the most appropriate first step to align the project with the new operational structure?

  • Initiate a new project to replace the current one, considering the extent of the organizational change is too significant.

  • Continue with the current project plan without modifications, keeping a record of changes in case they need addressing later.

  • Inform all stakeholders about the changes but wait for further instructions before taking any action.

  • Review and update the project charter and project management plan to align with the new operational structure.

PMI Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot