PMI Project Management Professional Practice Question

Your company is implementing a new enterprise resource planning (ERP) system. As a project manager, you notice the project implementation may significantly alter the work processes of several departments, potentially leading to resistance from employees accustomed to the old systems. Which of the following is the MOST effective approach for you to manage the impact of this project on the organization?

  • Engage department leads in the planning and implementation process to ensure alignment with existing workflows and garner support.

  • Inform the CEO about the potential changes and seek directives on how to manage the resistance.

  • Modify project objectives to minimize the impact on organizational workflows and reduce potential resistance.

  • Rely on the IT department to provide support during the implementation, assuming technical support will mitigate most concerns.

PMI Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot