PMI Project Management Professional Practice Question

You have been tasked to estimate the budget for a new project. Your current project is similar in scope to a completed project from two years ago, which had a final cost overrun of 10% due to unexpected regulatory changes. Considering this, what should your first step be in estimating the budgetary needs for the current project?

  • Start with a new budget estimate without consulting past projects as every project is unique and should be treated independently.

  • Use the same cost base as the past project, but add in a buffer for inflation over the past two years.

  • Review the financial documents and the lessons learned from the past similar project to identify areas that led to cost overruns.

  • Increase the total budget estimate by 10% based on the cost overrun from the past project.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot