You are the project manager in an automotive manufacturing firm, and your project involves the design of a new model of car. Which of the following would be the MOST appropriate first step in developing an effective Plan Schedule Management approach?

  • Update the project schedule model to match realistic schedule goals.

  • Start by defining the project milestones to determine the sequence of activities.

  • Proceed to assign staff to activities to confirm their availability and resolve any conflicts with resource calendars.

  • Hold planning meetings with team members to define the scheduling methodology and the scheduling tool.

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot