You are the project manager in an automotive manufacturing firm, and your project involves the design of a new model of car. Which of the following would be the MOST appropriate first step in developing an effective Plan Schedule Management approach?
Hold planning meetings with team members to define the scheduling methodology and the scheduling tool.
Update the project schedule model to match realistic schedule goals.
Start by defining the project milestones to determine the sequence of activities.
Proceed to assign staff to activities to confirm their availability and resolve any conflicts with resource calendars.
Developing the schedule management plan is crucial as it establishes the criteria and activities for developing, monitoring, and controlling the schedule. It sets the framework for schedule development and control, including methodologies, tools, and techniques to be used, which are all necessary for guiding the project team through the planning and executing stages of the project schedule.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are scheduling methodologies in project management?
Open an interactive chat with Bash
What tools are typically used for schedule management?
Open an interactive chat with Bash
Why is defining project milestones important in scheduling?
Open an interactive chat with Bash
Project Management Professional
Waterfall
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access