You are managing a software development project using an agile methodology. During a sprint retrospective, the team identifies a need to change the way they handle user story prioritization. What is the best approach to execute this change?
Wait until the end of the project to implement the change as a secondary release
Implement the change during the current sprint, allowing no time to be wasted
Have the project manager handle the change without involving the team
Implement the change in the next sprint, allowing the team to adapt quickly