PMI Project Management Professional Practice Question
You are managing a software development project and discover that a key team member has been reassigned to another high-priority project, leaving your project understaffed. What is the best approach to address this issue?
Proceed with the project as planned using the budget contingency to pay for extra hours
Assess the impact of the resource loss and adjust the project plan accordingly
Escalate the issue to senior management and request a replacement team member
Delay the project until a replacement can be found