Project Management Professional Practice Question

You are managing a project with a Budget at Completion (BAC) of $1,200,000. The latest status report shows an Earned Value (EV) of $400,000 and Actual Costs (AC) of $500,000. If you assume the team will continue to perform at the current Cost Performance Index (CPI), what is the best Estimate at Completion (EAC)?

  • $1,300,000

  • $960,000

  • $1,400,000

  • $1,500,000