Project Management Professional Practice Question

You are managing a project that involves processing confidential medical records. During the planning phase, what should be your first action to ensure the project meets all regulatory requirements for protecting patient information?

  • Conduct a detailed gap analysis comparing current data-handling practices with regulatory requirements.

  • Begin comprehensive privacy-compliance training sessions for all project team members.

  • Revise the stakeholder communication policy to increase transparency about data-privacy practices.

  • Identify and confirm all applicable laws, regulations, and standards that govern how patient data must be handled.

Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot