PMI Project Management Professional Practice Question
You are managing a project that has multiple stakeholders with varying levels of influence and interest in the project. To gain or maintain their support, it is essential to develop a Stakeholder Engagement Plan. Which of the following would BEST serve as the basis for developing your stakeholder engagement strategies?
General communication preferences of the project's stakeholders
An analysis of stakeholders' power, interest, expectations, and potential impact on project success
The geographical distribution of stakeholders' offices
Past experiences and lessons learned from previous similar projects