You are managing a project team that's distributed across different geographical locations with varying cultures and time-zones. Which of the following actions best outlines expectations for the project’s working environment to ensure smooth collaboration and efficient communication among team members?

  • Schedule regular weekly meetings at a fixed time that is most convenient for the majority of the team, expecting all members to adjust accordingly.

  • Rely on the flexibility of the team members to spontaneously communicate and collaborate as needed, without setting specific expectations.

  • Impose strict 9-to-5 working hours based on the project manager's time zone for all team members to ensure synchronicity.

  • Develop a comprehensive communication plan that includes the team's preferred communication tools, meeting schedules considering time zone differences, and expected response times for queries.