PMI Project Management Professional Practice Question

You are managing a project in an organization that is known for its rigid hierarchy and formal communication channels. Midway through the project, you observe that the slow decision-making process is impacting the project timelines. What should you do first to ensure project success without disrupting the organizational culture?

  • Implement informal communication channels to bypass the hierarchy for quicker decision making.

  • Increase team autonomy by allowing team members to make decisions without upper management approval to speed up the process.

  • Identify key decision-makers and leverage existing formal communication channels to expedite approvals.

  • Propose an organizational culture change to encourage a more flat and agile structure.

PMI Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot