You are managing a large construction project when you learn that the supplier for a critical set of materials has been acquired by another company. These materials are unique and vital for your project's completion. According to best practices in 'Project Procurement Management', what is the FIRST step you should take?

  • Review the procurement documents and any existing agreements to assess the implications of the supplier's acquisition on project deliverables.

  • Search for an alternative supplier or manufacturer.

  • Continue with the project, as the acquisition will not affect the supply of materials due to contractual requirements.

  • Cancel the material order and request a refund due to the acquisition in accordance with standard licensing agreements.

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot