Free PMI Project Management Professional Practice Question

You are managing a complex project with a large, cross-functional team. Which of the following actions would be the BEST approach to ensure that project information is maintained accurately and is readily accessible to all stakeholders?

  • Distribute updated project documents to team members via email at the end of each week.

  • Implement a centralized, integrated project management tool with version history and access control features, and establish a routine for regular updates by team leads.

  • Keep paper-based documentation in a centralized office location for team members to access and make updates as needed.

  • Maintain updated project documents in a shared network folder and rely on team members to check this folder for the latest updates before starting their work.