You are leading the closure of a software development project. Which of the following criteria is MOST crucial to decide whether the project can be successfully closed?
Confirmation that the software meets all functional and non-functional requirements specified in the project scope
All project team members agree that their tasks are complete
The project has stayed within the allocated budget
Final project documentation has been approved by the project sponsor
The correct answer is 'Confirmation that the software meets all functional and non-functional requirements specified in the project scope' because the success of the software development project largely depends on whether the software delivers the functionalities expected by stakeholders, adhering strictly to the requirements laid out in the project scope. Other options, while important in various contexts, do not singularly determine the success of the project closure as much as ensuring the fulfillment of project scope requirements.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are functional and non-functional requirements in a software project?
Open an interactive chat with Bash
Why is meeting the project scope critical for project closure?
Open an interactive chat with Bash
How does scope validation differ from project closure?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .