PMI Project Management Professional Practice Question

You are leading a software development project that involves multiple teams across different geographical locations. The project charter has been approved, and the high-level scope is defined. What is the next MOST critical action to ensure that the project resource requirements are correctly deduced?

  • Analyze current team competencies and compare them with project needs.

  • Begin developing the project team by acquiring the best available resources.

  • Conduct a stakeholder consultation to gather insights on resource preferences.

  • Review the project scope statement and work breakdown structure (WBS) to identify resource types and quantities.

PMI Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot