PMI Project Management Professional Practice Question
You are leading a project with the following characteristics:
- The client has provided a high-level vision but expects the project team to define the detailed requirements.
- The project involves the development of a new product using cutting-edge technology.
- The client expects to review and provide feedback on the product at regular intervals.
- The project team consists of highly experienced professionals from diverse backgrounds.
Which project methodology would be BEST suited for this scenario, considering the need for adaptability, client involvement, and the project team's expertise?
Agile methodology
Lean methodology
Waterfall methodology
Hybrid methodology