Project Management Professional Practice Question

You are leading a project with a diverse group of stakeholders, including one who has consistently demonstrated apprehension during group discussions, often deferring his opinion until after meetings via email. Considering personality indicators, what would be the most effective way to engage this stakeholder and ensure his concerns are addressed during the meetings?

  • You selected this option

    Encourage the stakeholder to communicate more during meetings by directly calling on him to share his opinions.

  • You selected this option

    Increase the frequency of group meetings to give the stakeholder more opportunities to feel comfortable speaking up.

  • You selected this option

    Schedule one-on-one meetings with the stakeholder before group discussions to understand and address his concerns privately.

  • You selected this option

    Suggest that the stakeholder communicates his concerns solely through email to avoid direct confrontation during meetings.

Project Management Professional
People
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot