You are leading a project that is nearing its completion. As part of the closing process, you must confirm that specific criteria are met to declare the project successfully closed. Which of the following would be an essential element to verify?
The overall project budget has been underspent by 10%.
The operational team is ready to assume control over project outputs.
The project deliverables have been completed according to the agreed-upon scope.
Stakeholder satisfaction has been reported above 90%.
Among the options provided, confirming that the project deliverables match the agreed-upon scope is necessary for successful closure. Deliverables must meet the requirements and acceptance criteria agreed upon with stakeholders. Stakeholder satisfaction alone does not guarantee that all project objectives were met, although it's an important aspect. Operational readiness may be part of the transition criteria but does not itself mark the completion of the project. Budget underspending is a financial metric that does not necessarily align with project success, as it might indicate unimplemented features.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are project deliverables?
Open an interactive chat with Bash
What does 'scope' mean in project management?
Open an interactive chat with Bash
Why is stakeholder satisfaction important, and how is it measured?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access