Free PMI Project Management Professional Practice Question

You are leading a project that is nearing its completion. As part of the closing process, you must confirm that specific criteria are met to declare the project successfully closed. Which of the following would be an essential element to verify?

  • Stakeholder satisfaction has been reported above 90%.

  • The overall project budget has been underspent by 10%.

  • The operational team is ready to assume control over project outputs.

  • The project deliverables have been completed according to the agreed-upon scope.

This question's topic:
PMI Project Management Professional / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot