PMI Project Management Professional Practice Question

You are leading a project team where the ground rules explicitly state that all members should provide updates in the weekly team meetings. However, you notice that one of the senior team members has consistently failed to do so, claiming their updates are 'not significant enough' for the meeting. What is the most effective action to take first to manage this ground rule violation?

  • Escalate the matter to higher management to ensure corrective action is taken.

  • Document the behavior and include it as feedback in the team member's next performance evaluation

  • Have a private conversation with the team member to understand their perspective and reaffirm the importance of following the team ground rules.

  • Discuss it with the team member during the next meeting to remind them of the ground rules

PMI Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot