Project Management Professional Practice Question

While validating the project schedule for a six-month product-launch initiative, the scheduler reviews Activity F (Develop training materials) in the network diagram. The forward pass shows an Early Start (ES) of day 15 and an Early Finish (EF) of day 21. The backward pass returns a Late Start (LS) of day 18 and a Late Finish (LF) of day 24. Management has asked for a realistic view of schedule flexibility so the team can reassign resources during peak workloads. Based on this information, how much total float is available for Activity F?

  • 3 days

  • 6 days

  • 0 days

  • 9 days

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot