While preparing for the stage-gate review of a prefabricated bridge section, the project manager learns that government regulators will examine weld certifications and dimensional tolerances, and the customer's engineer will look for evidence that the product meets previously agreed quality criteria. Before sending the bridge section for the formal review, the project manager wants to confirm that it already complies with all relevant standards and requirements. Which of the following project documents should the project manager consult FIRST to determine whether the finished deliverable meets the agreed quality thresholds?

  • Assess the impact of all approved change requests on the project's quality management plan.

  • Consult the quality metrics to verify that the deliverable adheres to defined quality standards.

  • Review the latest project management plan updates to check for any quality-related adjustments.

  • Analyze the most recent quality reports to determine if similar deliverables are functioning as intended.

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot