Project Management Professional Practice Question

While planning a multi-site infrastructure upgrade, you identify more than 50 stakeholders ranging from the CIO to end-user department assistants. Some hold authority to approve capital expenditures, whereas others are mainly concerned about day-to-day workflow impacts. To prioritize your engagement efforts, which stakeholder-categorization tool should you apply first?

  • Departmental organizational chart

  • Power/interest grid

  • Salience model

  • RACI matrix

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot