Project Management Professional Practice Question

While finalizing a contract with an external vendor, the project manager wants to ensure that the terms of the draft agreement align with the project's approved objectives. Which of the following actions provides the most reliable basis for verifying this alignment before signing the contract?

  • Discuss the draft agreement with the project sponsor and key stakeholders

  • Review the project charter, scope statement, and other relevant project documents

  • Identify potential risks in the agreement and propose mitigation strategies

  • Evaluate whether the objectives are feasible given current resources and constraints

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot