While executing a project, you identify that a previously documented risk has occurred, and it is impacting your project schedule. Which of the following actions should you take to address this situation as per the agreed-upon risk response plan?
Execute the predefined risk response plan that includes mitigation or contingency actions.
Update the risk register with the details of the risk occurrence.
Reevaluate the risk response plan for appropriateness.
Update the project stakeholders about the risk occurrence and impact.
When a documented risk occurs, the project manager should execute the predefined mitigation or contingency plan outlined in the risk response plan. This ensures the project team addresses the impact of the risk effectively. Notifying the stakeholders is part of communication management but not the immediate response to mitigate the risk. Updating the risk register is essential but comes after implementing the risk response. Reassessing the risk is also necessary, but it should follow the initial execution of the response plan.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a risk response plan?
Open an interactive chat with Bash
When should the risk register be updated in the risk management process?
Open an interactive chat with Bash
What is the difference between mitigation and contingency actions in risk management?
Open an interactive chat with Bash
Project Management Professional
Waterfall
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .