PMI Project Management Professional Practice Question

Which risk management process involves assessing the timing of identified risks in order to prioritize their response by determining which risks need immediate attention?

  • Risk Probability Assessment

  • Risk Urgency Assessment

  • Risk Impact Assessment

  • Risk Data Quality Assessment