Project Management Professional Practice Question

Which of the following project situations BEST justifies selecting a hybrid project management approach instead of using a purely predictive or purely adaptive (agile) life-cycle?

  • No part of the project can be defined upfront; requirements will emerge continuously through customer collaboration across the entire scope.

  • All project requirements are fully documented and unlikely to change, allowing the team to execute the entire project sequentially.

  • Several workstreams have well-defined, regulated requirements, while other workstreams involve exploratory research whose requirements are expected to evolve throughout delivery.

  • The project team has little experience with either predictive or adaptive methods and therefore wants to adopt the simplest possible lightweight process.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot