Project Management Professional Practice Question

Which of the following is the most effective way to ensure that project information and updates are communicated effectively to all stakeholders?

  • Communicating only when there are significant project updates

  • Relying on informal communication channels for all project updates

  • Using a single communication method for all stakeholders

  • Tailoring communication methods and frequency based on stakeholder needs

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot