Project Management Professional Practice Question
Which of the following is an example of a tool used to break down the project scope into smaller, manageable components?
Network diagram
Product backlog
Gantt chart
Work Breakdown Structure (WBS)
Which of the following is an example of a tool used to break down the project scope into smaller, manageable components?
Network diagram
Product backlog
Gantt chart
Work Breakdown Structure (WBS)
The Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project by subdividing the work into smaller, more manageable components. The product backlog, while also used to manage scope, is specific to agile methodologies and focuses on prioritizing user stories or requirements. Gantt charts and network diagrams are used for scheduling and depicting task dependencies, but not specifically for breaking down the project scope.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.