Which of the following best describes the purpose of evaluating stakeholder engagement needs?
To build trust among stakeholders
To identify stakeholders who can be excluded from the project
To optimize alignment between project objectives and organizational goals
To determine the appropriate level and type of involvement for each stakeholder