Which of the following best describes the purpose of a Risk Management Plan in the context of project management?
A diagram that visually plots the probability and impact of risks on the project objectives.
A chronological record of all the risks that have occurred throughout the project.
A component of the project management plan that describes how risk management activities will be structured and performed.
A document that lists all identified risks and their potential impact on the project.