PMI Project Management Professional Practice Question

Which of the following best describes the components that make up the Cost of Quality (COQ) in project management?

  • Costs incurred to meet quality standards, including both activities that prevent non-conformance and expenditures addressing non-conformances.

  • Costs related to the procurement of high-quality materials and technologies to accomplish project work.

  • Costs tied to hiring skilled labor and specialists for ensuring product quality.

  • Expenditures associated with warranty and maintenance work after project delivery.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot