PMI Project Management Professional Practice Question
Which activity is fundamental to keeping stakeholders informed about the ongoing realization of benefits from the project?
Redistributing project tasks among team members
Revising the project's work breakdown structure
Increasing the frequency of project status meetings
Providing regular updates on benefits realization