When selecting the most appropriate communication method or channel for a specific stakeholder group, which consideration should guide the project manager's decision?

  • The total communications budget and the project manager's technical skill level

  • Stakeholders' preferred communication style and the complexity or urgency of the message

  • Corporate branding standards and the number of lessons-learned reports from past projects

  • The fiscal-year closing date and the planned order of deliverable acceptance

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot