PMI Project Management Professional Practice Question

When planning a project schedule, which of the following is the most effective way to improve the accuracy of task duration estimates?

  • Ask each team member to provide their own estimates without any guidance

  • Rely solely on the expert judgment of the project manager

  • Add arbitrary time buffers to each task duration

  • Utilize benchmarks and historical data from similar past projects

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot