PMI Project Management Professional Practice Question
When planning a project schedule, which of the following is the most effective way to improve the accuracy of task duration estimates?
Ask each team member to provide their own estimates without any guidance
Rely solely on the expert judgment of the project manager
Add arbitrary time buffers to each task duration
Utilize benchmarks and historical data from similar past projects