When managing a project, you discover repeated violations of the team's ground rules concerning timely communication. If one particular team member continues to miss deadlines for updates, which of the following actions is BEST to rectify this behavior?

  • Escalate the issue to higher management for disciplinary action.

  • Issue a general reminder to all team members about the importance of timely updates.

  • Meet individually with the team member to discuss the importance of timely updates and any challenges they are facing.

  • Penalize the team member by reducing their role in the project.

PMI Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot