When evaluating prospective sellers in the 'Conduct Procurements' process of a Waterfall project, which factor is the project manager likely to prioritize in the decision to ensure alignment with project constraints and delivery timelines?
Choosing sellers based solely on past relationships without verifying their proposal against the current project's procurement documentation.
Seeking the lowest cost proposal to meet budgetary constraints, potentially sacrificing the alignment with project specifications.
Prioritizing vendors with the fastest delivery commitments, regardless of their understanding of technical specifications.
Assessing proposals for consistency with procurement documentation requirements, such as compliance with legal and technical specifications.