PMI Project Management Professional Practice Question

When defining escalation paths and thresholds for a project, which of the following factors should be considered to determine the appropriate level of escalation for an issue?

  • The urgency of the issue and the time required to resolve it

  • The complexity of the issue and the technical expertise required to address it

  • The potential impact of the issue on the project's objectives

  • The authority level of the project manager and their ability to make decisions

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot