When defining escalation paths and thresholds for a project, which of the following factors should be considered to determine the appropriate level of escalation for an issue?
The potential impact of the issue on the project's objectives
The urgency of the issue and the time required to resolve it
The complexity of the issue and the technical expertise required to address it
The authority level of the project manager and their ability to make decisions
The potential impact of an issue on the project's objectives, such as scope, timeline, budget, and quality, is the most critical factor in determining the appropriate level of escalation. Issues that pose a significant risk to meeting project objectives should be escalated to higher levels of management or governance boards for prompt resolution. The urgency of the issue, while important, is not the sole determining factor, as some urgent issues may have minor impacts. The complexity of the issue and the authority level of the project manager are relevant considerations but should be evaluated in conjunction with the issue's potential impact on project objectives.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why is the potential impact on project objectives the most critical factor for escalation?
Open an interactive chat with Bash
What is the difference between urgency and impact when determining escalation paths?
Open an interactive chat with Bash
How can project managers determine when to escalate an issue?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .