When a change request is approved, what should the project manager do next to ensure the project continues to progress?
Conduct a risk assessment of the approved change
Update the project management plan and communicate the change to stakeholders
Confirm the change has been implemented and retroactively update the project plan
Submit another change request to refine the approved change