PMI Project Management Professional Practice Question
What proactive approach must a project manager take to adapt the project scope effectively in the face of evolving market trends and regulatory demands?
Institute an environmental scanning process to identify relevant trends and regulatory changes
Limit the review of the business environment to the project planning phase
Wait for changes to crystallize before considering their impact on the project, in order to steward resources properly
Focus on internal project performance metrics