PMI Project Management Professional Practice Question
What is the most effective strategy to ensure that stakeholders are kept informed about the progress of the value gained from a project?
Updating the project's Gantt chart to reflect completed tasks.
Distributing regular progress reports outlining benefits realized and the progress towards achieving those benefits.
Convening an annual meeting to review the project's value gain at the end of the year.
Sending out detailed technical specifications of project deliverables to all stakeholders.