PMI Project Management Professional Practice Question
What is the most appropriate initial step in determining how to address and manage compliance needs for a new project?
Develop a risk management plan to mitigate potential compliance threats
Measure current compliance levels against industry standards
Identify all applicable compliance requirements for the project
Classify the project's deliverables according to their importance for compliance