Free PMI Project Management Professional Practice Question

What is the most appropriate action to take when a quality gap is identified in a project deliverable?

  • Ignore the quality gap and proceed with the project as planned

  • Implement changes to address the quality gap without further analysis

  • Document the quality gap in the project report and alert senior management

  • Analyze the root cause of the quality gap and recommend appropriate corrective actions

This question's topic:
PMI Project Management Professional / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot