What is the key focus of the Control Scope process in project management?

  • Breaking down the project scope into smaller, more manageable activities

  • Monitoring the project and product scope and managing changes to the scope baseline

  • Formalizing the acceptance of the completed project deliverables by the stakeholders

  • Defining the functional and non-functional requirements of the project deliverables