PMI Project Management Professional Practice Question
What Agile ceremony is BEST suited for directly involving stakeholders in the process of iteration review to provide immediate feedback that will shape the subsequent sprint?
Sprint Planning, which is intended for the team to outline the work for the upcoming sprint and not for reviewing completed work with stakeholders.
Daily Scrum, where stakeholders observe the daily coordination of the team to provide their input on task prioritization.
Sprint Retrospective, which is primarily a team meeting focused on self-improvement rather than stakeholder feedback.
Sprint Review, as it provides a platform for demonstrating the increment developed during the sprint and gathering feedback to inform the next steps.